Page 1 Page 2 Page 3 Page 4 Page 5 Page 6 Page 7 Page 8 Page 9 Page 10 Page 11 Page 126 50,000 new homes for Sydney are held up in the Planning System Dwellings Location Reason For Delay 5400 Wilton West Delays by many government agencies. 3500 Wilton South East DPE starting assessment process again. 1600 Governors Hill, Wilton Delays by Government agencies. 650 Schofields Council not responding to the DA, changing their mind about agreed upon aspects of the development and design . 170 Lilyfield Various road blocks put up by council. 1500 Auburn Council were placed under administration. Additional delays caused awaiting the completion of the Parramatta Road Corridor Urban Transformation Strategy. 882 Granville Railcorp taking an excessively long period of time to undertake design compliance assessment. 5000 Cooks Cove Delay with government agencies. 800 Parramatta Greater Sydney Commission decided to change planning rules after development application was lodged and approval had been issued by Parramatta City Council. 190 Meadowbank Rejection by PAC of winning design from design excellence competition which was required by PAC as pre-existing condition of consent. 654 Epping Council amalgamation process forced the assessment process to recommence. New Council administrator made a decision to defer the project. 201 Chatswood Council refuses to approve mixed uses in Commercial Core. 830 North Ryde Council refused to assess the DA, despite application complying with requirements, because of disagreement with Department of Planning & Environment regarding anticipated growth rates in the area. 270 Kogarah Roads and Maritime Services are not responding to Department of Planning & Environment. 120 Carlton Roads and Maritime Services are not responding to Department of Planning & Environment. 7000 Moorebank Transport studies / Network Plan. 700 Castle Hill Masterplan and zoning maps taking long time to be produced and approved. 1000 Macquarie Park Draft Framework Plan is taking a significant amount of time to be produced and approved. 1000 Kingsgrove Council are not willing to rezone land from employment uses to residential and the Greater Sydney Commission is encouraging this policy stance. 400 St Leonards Planning Panel awaiting outcome review of various strategies in particular the St Leonards to Crows Nest Plan. 500 Frenchs Forest Roads and Maritime Services and other government agencies cannot agree on desired traffic outcomes. 315 Leichhardt Department of Planning & Environment and Sydney East Planning Panel have taken a long time to determine and process. 408 Brookvale Council requested the proponent withdraw the application until the Brookvale Structure Plan was finalised. Currently structure plan is 6 months overdue. 450 Parramatta Council have a lack of staff and resources to cover the workload. Length negotiations to produce a Voluntary Planning Agreement which was reasonable for the developer and allowed the project to be financially feasible. 750 Kellyville Land swap negotiations and acquisition – councils and state authorities are taking a very long time undertaking this process. 777 St Leonards Transport for NSW and Roads and Maritime Services have requested Council defer further consideration of the planning proposals until the St Leonards / Crows Nest Precinct Planning is complete – no time frame is provided although this could be well over a year. 225 Croydon Park Department of Planning & Environment did not enforce the council recommendation, amalgamation has slowed down councils response. 964 Parramatta Lack of Council staff and resources to undertake the assessment in a timely manner, state agencies taking a long time respond and provide information, lengthy negotiations with council to put together a Voluntary Planning Agreement which was reasonable and allowed the development to be financially feasible. 5094 Parklea State agencies refusing to facilitate or attend meetings, State agencies refusing to provide data needed for traffic modelling. 173 Parramatta Lack of Council staff and resources to undertake the assessment in a timely manner and lengthy negotiations with council to put together a Voluntary Planning Agreement which was reasonable and allowed the development to be financially feasible. 1200 Merrylands Under resourcing at Cumberland Council due to council amalgamation process. 1100 Marrickville Council are not progressing the application through the exhibition stage as requested by Department of Planning & Environment. 169 Haymarket Unreasonable request by Council for costly CAD and physical model. 147 Alexandria Pre-DA for Stage 1. Misinterpretation of Apartment Design Guide of 100% natural ventilation. All three times, Council requested different design changes. 17 Leichhardt Council unwilling to work on possible design changes. 36 Leichhardt Council is unwilling to work with developer despite NSW Department of Planning & Environment indicating that growth is anticipated along the Parramatta Road Corridor. Gone to Land and Environment Court. 35 Leichhardt Council is unwilling to work with developer despite NSW Department of Planning & Environment indicating that growth is anticipated along the Parramatta Road Corridor. Gone to Land and Environment Court. 422 St Leonards Transport for NSW has put a halt on planning proposals in the area, we are unable to progress and have been told it could be a year or longer before DPE and TFNSW finalise future plans. The area sits on the boundary of three councils who are subject to two separate merger proposals which causes further delays. 515 Dee Why Lack of Council resources through amalgamation and protracted PP process.